Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 157: 2008-202-00 EXP TUCANNON WATERSHED HABITAT: PROTECT AND RESTORE
Project Number:
Title:
Protect and Restore Tucannon Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Tucannon 100.00%
Contract Number:
73982 REL 157
Contract Title:
2008-202-00 EXP TUCANNON WATERSHED HABITAT: PROTECT AND RESTORE
Contract Continuation:
Previous: Next:
73982 REL 130: 2008-202-00 EXP TUCANNON WATERSHED HABITAT: PROTECT AND RESTORE
  • 73982 REL 187: 2008-202-00 EXP TUCANNON WATERSHED HABITAT: PROTECT AND RESTORE
Contract Status:
Closed
Contract Description:
Background:  The Tucannon River basin is located within the ceded-area of the CTUIR in Southeast Washington State, in Columbia and Garfield counties. The system-wide restoration objective for the Tucannon River is to improve habitat conditions for Endangered Species Act (ESA) listed species (Snake River Spring Chinook and Steelhead) for all life history stages.  It is expected that improved habitat conditions will lead to an increase in the abundance of listed species returning to the river.  The long term goal of increasing abundance should lead to de-listing of the species, which is the overall recovery goal for the system. Previous assessment efforts (CTUIR, WDFW, CCD and SRSRB) have identified the habitat-limiting factors associated with the decline of ESA-listed populations.  

The updated Tucannon River Geomorphic Assessment & Habitat Restoration Study (Anchor QEA, 2021) identifies and prioritizes stream reaches and restoration actions which would best improve watershed habitat conditions for salmonids. Earlier, focusing on the high priority areas for Tucannon spring Chinook, the Columbia Conservation District (CCD) coordinated the development of an initial habitat restoration plan for the Tucannon River from RM-20 upstream to RM-50; the CCD continued to work with the Snake River Salmon Recovery Board (SRSRB), through the Tucannon River Programmatic Habitat project, and extended the 2011 Tucannon River restoration plan from RM-20 downstream to the confluence of the Snake River.  This Conceptual Restoration Framework (2011 Plan) prioritized projects into three Tiers (1-3) based on the projected effects of implementation as a benefit to Snake River spring Chinook, cost-efficiency relative to those benefits, and the feasibility of construction.

The revised Conceptual Restoration Study and Plan (2021 Plan) continues this practice, prioritizing projects into Tiers (1-3), but now based on revised and more explicit prioritization goals derived from key parameters that characterize the geomorphic conditions in the river: channel and floodplain connectivity, channel complexity, excess transport capacity, in-channel (LWD) structure and pool frequency. In general terms, the plan’s focus is on: removing channel and floodplain confining features like levees; emphasizing additional LWD placements; and incorporating gravel augmentation to sustain sediment transport, as strategies to accelerate channel aggradation and lateral movement in areas where channel confinement and floodplain isolation are driven by incision.  

The 2021 Plan identifies loss of floodplain connectivity as the major driver in reduced channel complexity, degraded riparian areas, and diminished resilience -- including a loss of stream temperature regulation through the mechanism of hyporheic exchange. The restoration actions identified and outlined in the 2021 Plan are focused on instream methods to reduce floodplain confinement, increase channel length and reduce excessive stream power. With these refined and refocused prioritization goals, the CTUIR contract staff and project implementers will select work areas and develop habitat restoration approaches in the Tucannon within a Program framework that better emphasizes floodplain connectivity as the key component in restoring habitat access and improving conditions for adult and juvenile Snake River spring and fall Chinook, steelhead, and bull trout throughout the watershed.

Overview: The Snake River Salmon Recovery Board (SRSRB) manages the Tucannon River Programmatic Habitat Project (2010-077-00) through a parent contract for the operations support, management organization, implementation assistance, and reporting described in this summary. The goal of the Tucannon River programmatic is to restore habitat function and natural channel processes in the spring Chinook priority restoration reaches of the Tucannon River, leading to improved population productivity and abundance.  The CTUIR manages this contract as a contribution in support of programmatic goals, consistent with the CTUIR River Vision: a desired riverine system that is shaped and maintained by the dynamic interactions and interconnections of its natural physical and ecological processes. The restoration actions proposed for implementation in the prioritized river segments promote and enhance the interconnected nature of the five primary touchstones of the Tribes' Vision: a) hydrology, b) geomorphology, c) connectivity, d) riparian community, and e) aquatic biota.  

Major limiting factors influencing the condition of these touchstones throughout the project reaches proposed for treatment in the watershed, include:  
  â€¢ Anthropogenic modifications affecting and causing the loss of natural channel forming processes that link the Tucannon River to its floodplain;
  â€¢ Loss of key in-channel habitat complexity and structure, including diversity and quantity, especially in the form of gravel sorting, varied velocities, and pools associated with recruitment of large wood; and
  â€¢ Elevated summer water temperature, and reduced flow duration.
_________________________________________
Contract Summary: This contract continues the CTUIR role anticipated in the Accords (BPA) and the Tucannon Habitat Programmatic Project: to inform and conduct project evaluation, selection, management, implementation planning, data collection, monitoring, outreach and other tasks, where tribal staff can provide expertise; and to be an implementer of the on-the-ground project construction activities for projects identified in the Programmatic work plan, and sub-regional Snake River Salmon Recovery Plan. Contract tasks include identifying and sequencing projects for implementation pursuant to the prioritized restoration strategy of the Habitat Programmatic, and consistent with the Tribes' First-Foods paradigm and River Vision principles; the CTUIR staff will partner with SRSRB participants and others to implement the priority projects.

This yearly contract supports the recurring development of future habitat project concepts, refinement of restoration approaches, the production of engineered designs for selected projects, implementation work-planning and construction scheduling for approved projects, and the build-out of completed projects.

  â€¢ Ongoing: In this contract term, CTUIR staff continues to support and maintain watershed coordination with SRSRB, CCD, WDFW and Nez Perce Tribe, through ongoing communication and collaboration, shared work-tasks, and monthly and quarterly meetings. The CTUIR is also a member of and attends the meetings of the SRFB Lead-Entity committee, to review, rank and select projects for funding in the State of Washington (RCO) Salmon Recovery sub-regional process for the Snake River. CTUIR staff attends SRSRB (Board) Meetings on a monthly basis, and acts as the RTT Board Liaison to ensure pertinent information is transferred from the RTT to the Board. The CTUIR continues project development efforts and implementation tasks addressed to improving habitat structure and function at Project Areas (PA) throughout the Tucannon Watershed.

  â€¢ Current: Habitat project development, design and implementation emphases in the current contract period are at: PA-15/17 and PA-27/28.1. Longer-term efforts at PA-18 (Hartsock) continue to be evaluated and monitored. Actions proposed in these project areas are identified as a high priority for habitat improvements (Anchor QEA, 2021), and focus on promoting sediment transport and increasing the amount of large wood debris (LWD) to increase channel complexity and floodplain connectivity, the highest priority outcomes for spring Chinook in the Tucannon. Description of the project areas with respect to existing natural processes and habitat conditions is to be provided in the associated project Design Reports, along with the specific physical and biological objectives that the proposed restoration treatments are expected to achieve for each phase of the project design and the construction build-out of the habitat features for these project areas.  
___________________________________________
Workplan (FY22/23): CTUIR will lead the concept development, design progression, modeling and analyses, reviews, clearances, implementation planning, and management and supervision of: pre-construction tasks, site preparation, materials acquisition, permitting, and design finalization in PA-15/17, and for the irrigation efficiency component (Phase-II) and floodplain connection (Phase III) projects at PA-27/28.1. The proposed design features for each project are intended to benefit spring Chinook by providing better refuge and spawning habitat for adults, reducing redd-scour during winter flood events, and increasing rearing habitat and over-winter survival for juveniles. Contributions to the overall watershed-scale goals of the Tucannon Restoration Plan (2021 Plan) will be described in the Basis of Design Reports (BDR) for each of the phased components of the design products for the Project Areas.

(1)  PA-15/17 (FY22-24): work with local landowners to confirm restoration project commitments on the upper 1.5 miles (PA-15/17). The intention is to be ready for implementation of Phase-II of the PA-17/18 (now PA-15) design in 2024.
  --  Ongoing restoration planning with additional local landowners to determine interest in a future restoration project;
  --  Complete landowner agreements verifying landowner participation in the restoration project;
  --  Continue project design review with Tucannon implementers and landowners in PA-17, currently at 60-80% design stage;
  --  Work through project design to 100% with Tucannon implementers and landowners, identify project elements and start permitting during Spring 2024.  
  --  Project implementation would start summer of 2024, if momentum continues with willing landowners in PA-15/17.

Note (caveat): Included in the Hartsock Floodplain Restoration Project (WDFW), Phase-1 of the Hartsock project area (PA-18) was completed in summer of 2017. CTUIR staff expects these next phases (PA-15/17) and beyond to be challenging as we move from public to private lands. CTUIR anticipates needed flexibility in the dates for project design completion and implementation planning, to adapt to changing circumstances, and adjust time frames as concept development and commitments evolve.

(2)  PA-27/28 (FY22/23): development and preparation for implementation of the PA-27/28.1 (Phase-III) project design in Summer 2023.
  --  In addition to initial development of Phase-III, CTUIR staff will also manage project implementation for the irrigation efficiency component at PA-27/28 (Phase II) in FY22.
  --  The design focus for the project area is on improving the multiple habitat structure, floodplain connection, and stream function deficiencies associated with this reach of the Tucannon River;
  --  The anticipated 30-60% designs for Phase III will identify the following types of measures that can address spring Chinook limiting factors, and the touchstones of the CTUIR River Vision: 1) Increasing large woody debris loading to promote instream habitat quantity, quality/complexity; 2) Increasing instream habitat quantity/quality with habitat boulder clusters; 3) Hydraulically reconnecting the river with its floodplain through side channel construction (improved off channel habitat, floodplain vegetation); 4) Restoring riparian forest vegetation to promote future large wood loading and summer water temperature reductions; 5) Replacing downstream bridge to increase flood conveyance, and reduce upstream geomorphic effects;
Account Type(s):
Expense
Contract Start Date:
04/01/2022
Contract End Date:
03/31/2023
Current Contract Value:
$409,729
Expenditures:
$409,729

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Habitat Project Implementation Management and Contract Administration 03/31/2023 03/31/2023
Compliance documentation and assistance for environmental and cultural resource clearances B: 165. Environmental Compliance Documentation and Clearance: habitat restoration and enhancement project (PA-27/28.1) 03/31/2023 03/31/2023
Productive, effective, cooperative relationships and implementation actions with partner entities C: 191. Coordinate proposed habitat restoration actions and implementation planning (Middle-Snake) 03/31/2023 03/31/2023
Portray the work; promote understanding, support and appreciation of completed restoration actions D: 99. Tucannon River: Outreach to Private Landowners and Public Lands Managers 03/31/2023 03/31/2023
Provide program guidance: develop priority habitat project list and implementation work plan or schedule E: 114. Identify, evaluate, prioritize and select projects for habitat improvement 03/31/2023 03/31/2023
Produce final construction design and site plan (90-100%): Tucannon (PA-15) F: 175. Final Engineering and Design (80-100%): Floodplain Connection & Habitat Complexity Project (PA-15/17) 03/31/2023 03/31/2023
Develop project concepts, produce preliminary and subsequent designs, and plan for implementation G: 175. Design Specifications and Engineering: PA-27/28 (Phase III) - Habitat Complexity & Floodplain Reconnection 03/31/2023 03/31/2023
Native plant restoration plan to recover and maintain streambank, riparian zone and floodplain plant communities H: 47. Establish Native Plant Restoration Plan and Species List (Riparian & Floodplain Plant Community): PA-27/28 03/31/2023 03/31/2023
Provide pre-construction project management activities; supervise the design build-out: I: 100. Site Preparation, Materials Management, Field Engineering, Quality Assurance, Construction Oversight (PA-27/28) 03/31/2023 03/31/2023
Collection and assessment of trend data for 4 shallow alluvial aquifer wells J: 115. Assess Trends (Habitat Condition): monitor water level in the alluvial aquifer (PA-18): Year-5 03/31/2023 03/31/2023
Submit a 2-year (Annual) Progress Report for 2021 and 2022 L: 132. Progress Report (2-year): 2021 and 2022 (01/01/2021 - 12/31/2022) 03/31/2023 03/31/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Habitat Project Implementation Management and Contract Administration
B 165 Environmental Compliance Documentation and Clearance: habitat restoration and enhancement project (PA-27/28.1)
C 191 Coordinate proposed habitat restoration actions and implementation planning (Middle-Snake)
D 99 Tucannon River: Outreach to Private Landowners and Public Lands Managers
E 114 Identify, evaluate, prioritize and select projects for habitat improvement
F 175 Final Engineering and Design (80-100%): Floodplain Connection & Habitat Complexity Project (PA-15/17) 01/25/2022
G 175 Design Specifications and Engineering: PA-27/28 (Phase III) - Habitat Complexity & Floodplain Reconnection 01/25/2022
H 47 Establish Native Plant Restoration Plan and Species List (Riparian & Floodplain Plant Community): PA-27/28 01/25/2022
I 100 Site Preparation, Materials Management, Field Engineering, Quality Assurance, Construction Oversight (PA-27/28)
J 115 Assess Trends (Habitat Condition): monitor water level in the alluvial aquifer (PA-18): Year-5 01/25/2022
K 185 Periodic Status Reports for BPA
L 132 Progress Report (2-year): 2021 and 2022 (01/01/2021 - 12/31/2022)